Roller – Lockout Tagout Procedure

Document ID:
Department Owner:
Fleet Operations
Effective Date:
04/30/2020
Revision:
0

(Performed by Authorized Personnel Only)

Manufacturer: Bomag

Model: 120AD-4

Potential Energy Hazards Electric
Air
Pneumatic
Gravity
Mechanical
Gas
Hydraulic
Water
Method of Neutralizing Energy LOTO
Disconnect Lines
Block/Bleed
Release pressure
Set Fire Watch
Confined space permit
Permits Required Safe Work Hot Work Line Blanking Confined Space

Lockout (Shut-Down Procedure)

  1. Always clean machine and engine thoroughly before starting maintenance work.
  2. For maintenance work stand the machine on level ground.
  3. Always remove the main battery switch for all maintenance work.
  4. Preform maintenance work only with the motor switched off.
  5. Relieve hydraulic pressures before working on hydraulic lines.
  6. Before working on electric parts of the machine disconnect the battery and cover it with insulation material.
  7. When working in the area of the articulated joint attach the articulation lock (transport lock).

Start-Up Procedure

  1. Reinstall main battery switch
  2. Remove insulation material and reconnect battery after working on electric parts of the machine.
  3. Remove the articulation lock (transport lock).